These Two States Are On Pace To Have Some Of The Highest Electric Bills In The Nation

The Daily Caller
Original Story by The Daily Caller
November 19, 2026
These Two States Are On Pace To Have Some Of The Highest Electric Bills In The Nation

Regulators paused PJM’s one-time reliability backstop to secure power for data-center growth on the nation’s largest grid, while probing who should bear the costs. The decision, effective through February 28, 2027, follows a September 29 FERC order that accepted most of PJM’s plan but flagged the cost-allocation framework as unjust and pending revision. The delay introduces uncertainty for a 6.8 GW capacity solicitation and for timing of a December capacity auction for 2029/2030, with implications for how new load is funded and whether households are shielded from rising charges. Stakeholders push for fair allocation, faster infrastructure gains, and clarity on risk to reliability and prices as the region grows. The broader outcome remains dependent on revised cost-sharing rules and improved load forecasting.

Dive Deeper:

  • PJM Interconnection operates the grid for about 67 million people across 13 states and Washington, D.C., and planned to solicit offers for roughly 6.8 gigawatts of new capacity between Sept. 30 and Oct. 21.

  • FERC’s Sept. 29 order largely backed PJM’s plan but identified several items requiring work and delayed the procurement until Feb. 28, 2027, while leaving dates for revised filings open and stating the future cost allocation must be just and reasonable.

  • The commission questioned how the costs of serving data-center growth would be divided among existing customers and new large loads, signaling potential shifts in who pays.

  • Advocates for data centers argued that costs should align with where growth occurs and that infrastructure investments receive proper recognition, while criticizing any allocation that would burden households or residential customers.

  • Observers noted that the five-month delay does not appear to threaten reliability or near-term price risk, but they emphasized that true risk rests in whether the final allocation is fair and incentives timely infrastructure delivery.

  • Maryland officials estimated the procurement could affect up to $562 million on customers of two utilities, Baltimore Gas and Electric and Potomac Edison, highlighting regional sensitivity to how costs unfold.

  • FERC also removed a provision allowing some cooperatives and municipal utilities to opt out of the backstop, labeling that approach unfair to other data-center-serving utilities.